FAB Preparation Checklist

The table below provides a list of preparation items and checks to perform prior to the FAB Deployment and Set Up process.

Item No.

Area

Description

Comments

Status

1

VPN into customer network

(If necessary)

VPN details and access to customer's network

If VPN is required to connect to the customer's network. Please provide the VPN details to the Named Resources.


2

SAP GUI

SAP GUI connection details to Target SAP environments, including Front End gateway server if applicable

Application Server, Instance Number, System ID & SAPRouter String


3

SAP Access

SAP Login Accounts for the Named Resources

User accounts to run SE37, SE38, SE80, SE16n, SE11, SE16, SE10, ST05, SICF, /IWFND/MAINT_SERVICE, SM59, SPRO, /IQX/FAB, /IQX/FAB_CONFIG, /IQX/FAB_ANALYSIS, /IQX/FAB_DATA, /IQX/FAB_RECOVER
etc. (typically developer access)

Functional access to process (for SAP backend only)
Functional transactions for testing purposes e.g. MIGO, MIRO, CO11N, PA30 etc.

Dev access to enable deployment and configuration of FAB.

For hub deployment, SAP access is required to both front end and backend systems.


4

SAP Developer

Developer Key for one of the Named DEV Resources

Assign ABAP Developer key


5

SAP System Readiness

Review the Document “FAB Deployment Options and Prerequisites V2.2” for system requirements

Recommended Gateway Component SAP_GWFND 740 should be on SP-Level 015.


For Cloud Deployment Assistance

6

SCP

Gateway admin access on cloud



7

SCP

WebIDE access to upload apps



8

SCP

Access to the Cloud Cockpit

HTML5 Application


9

SCP

Access Fiori Configuration Cockpit



10

SCP

Fiori Launchpad URL